Communication Facilities at VWW
The next goal of the VWW project is to develop and implement
Telecommunication facilities from BSNL at the entire project. The
communication cabling work will disseminate throughout the layout. The
facilities will include Land line connections & Broadband High
Speed Cable internet connections. The action to execute communication
facilities has been intiated in Phase - 1. Soon it will start in Phase
-3 also.
Entrance Arch
100% work complete. A project logo has been
affixed on arch. An Elegant entrance is being
built to welcome the visitors and the residents to the Project.
Strom Water Drains
100% work done.
Storm Water drains are intended to drain excess rain and ground water
from paved streets and sidewalks. Any sudden large rainfall that
exceeds the sewage treatment capacity will be allowed to overflow to
the storm water drains.
Water Supply & Sanitation
100% work done.
The Sanitation & Water supply system will collect the
wastewater
and will get passed on to the Sewage treatment plant. The Water supply
is designed in a way to allow regular or time limited intervals based
on the supply.
Electrical Works
100% work done. Electrical works
involves power management from a single receptacle to the entire
facility at whispering woods. At VWW our electrical arrangement
includes power distribution design, engineering, processing and
equipment installation works. It is well
connected to external supply.
Road works - WBM layer 1
100% work done.
The road work WBM layer 1 formation is completed 100 %, and soling is
perfectly set for all phases at VWW for long lasting roads at the
layouts. Necessary care is taken to retain the quality of the work.
Road works - WBM layer 2
100% work done.
Over Head Tank 1
100% work done. The overhead tank is now ready to
take up water
throughout phase 3. The image of over head tank shows the interior and
exteriors are completely done and it has been white colored to give an
aesthetic look.
Over Head Tank 2
100% work done. The overhead tank is now ready to
take up water
throughout phase 3. The image of over head tank shows the interior and
exteriors are completely done and it has been white colored to give an
aesthetic look.
Sewage Treatment Plant
100% work over.
The STP (2) now completed 100%. Sewage Treatment. The source of Sewer
Treatment Plant is to safely and effectively treat the layouts
wastewater
by the process of removing contaminants from wastewater both runoff and
domestic. It includes physical, chemical and biological process to
remove physical, chemical and biological contaminants. Where as STP -
1 and STP - 3 are in progress and will updated in the
newsletter regularly.
Athletes Arena
65% work complete.
Athletes Arena at the Phase 3 all set about
65%. The works in the Fields & Arena will include the Kids play
areas, Cricket Pitch, Outdoor Theatre (Amphi Theatre), Jogging Track,
Skating
Rink,Tennis courts & Basket & Volley Ball courts.
.
Compound Wall
95% work done.
A strong 7 foot compound wall surrounds the complete layout for safety
& security.
Landscape Gardens
65% work complete.
The Garden landscapes along with the fruit orchards are situated to
enhance the beauty of whispering woods. They are under good care
by the professional gardeners.
Nursery Park
Nursery park has been construtced newly to add on a quality of
whispering woods phase-3
Club House
5% done. The Club House plans have been drawn and
finalised, and the work is set to begin shortly.
|